Version 28 (modified by gaew, 15 years ago) (diff)

--

Data collection status

This page describes the status of upcoming flights in the current (2009) flying season.

For an update on the operational status of the ARSF for data collection see this page.

Note: the actual flight date is dependent on operational restrictions and the presence of suitable weather conditions. All data are collected on a "best endeavours" basis.

Please contact Gary Llewellyn (Science / operations coordinator) if you have any questions or concerns: gaew@… (01865 374 391)

Projects completed in 2009

Project Location PI Date of final data acquisition
AST08/01 Glocestershire Astrium February

For status on data processing for flights that have been flown, see this page.

Status of direct access UK projects in the 2009 flying season

Project Location PI Status Data collection Comments
GB08/19 London Martin WoosterHigh PriorityData acquired in August 2008Requires thermal data||
GB08/02 Delamere Forest Mark Danson Priority Final acquisitions in 2009 Multiple acquisitions, requires synchronous LiDAR data. First LiDAR data acquired in March 2008
GB08/13 Lake Vyrnwy Mat Disney Priority Two acquisitions, requires synchronous LiDAR data
GB08/08 Wytham Woods Richard Harding Priority Opportunistic acquisitions Multiple acquisitions, requires near-synchronous LiDAR data. Continuation from 2008
GB08/12 Borth Bog Angela HarrisPriority August Single acquisition
GB09/11 Abernethy Forest Tim Malthus Priority June
GB09/04 Coed Y Brenin Sarah Taylor March/April
GB09/07 West coast Andreas Baas Probably will be split into a North and South sections
GB08/10 Denny Wood Ross Hill First acquisition planned for March/June Deferred from 2008.
GB08/06 Peak District Julia McMorrow End of June/Start of July Deferred from 2008.
GB08/15 Eaves Wood Alan Blackburn Partially supported
GB07/07 Inverclyde Tim Malthus Partially supported
HY05/06 Pitlochry Mark Cutler
GB03/01 Fiskerton-Barlings Jim Williams LiDAR data required
GB06/02 Frieston Shore Tom SpencerPartially supported, LiDAR data required
GB01/12 Ripon Anthony Cooper Partially supported, LiDAR data required
GB07/12 Peak District Andrew Wilson & Martin Wooster Early spring Needs to match the 'burn period'

Status of direct access overseas projects in the 2009 flying season

Project Location PI Status Data collection Comments
EU09/02 Alps David Rippon Priority August
GB07/09 Alps Martin Kirkbride August Combined with GB07/10
GB07/10 Alps Ben Broke August Combined with GB07/09
EU09/06 Iceland David Graham Priority August
EU09/01 Iceland Johnathan CarrivickInvited resubmission August

Status of Consortium (or Standard) grant funded projects in the 2009 flying season

Project Location PI Status Data collection Comments
ET07/01 & ET07/04 Ethiopia Tim Wright High Priority November Not supported in 2008 due to adverse conditions

Status of commissioned access projects in the 2009 flying season

Project Location PI Status Data collection Comments
CEH07/04 Moorhouse/Ribblehead/Hellifield Andrew Wilson No simultanious fieldwork, LiDAR data required
HY05/02 Ayreshire Coalfield Graham Ferrier/Gisela Ager Priority
BGS08/01 Firth of Clyde Gisela Ager Priority Awaiting project details, LiDAR data required
BGS08/02 Firth of Forth Gisela Ager Awaiting project details, LiDAR data required
BGS08/03 Glasgow Gisela Ager Awaiting project details
BGS08/04 South Lanarkshire Gisela Ager Awaiting project details
BGS08/05 Lothian Gisela Ager Awaiting project details
BGS08/04 Fife Coalfield Gisela Ager Awaiting project details
GB06/08 Weardale Claire Flemming
GB06-09 Isle of Wight BGS Original data set may be recoverable||

Projects completed in 2008

Project Location PI Date of final data acquisition
ET07/03 Ethiopia Graham Ferrier 2008
ET07/05 Ethiopia Graham Ferrier 2008
ET07/06 Ethiopia Ian Willis 2008
ET07/07 Ethiopia Richard Bates 2008
GB07/04 Hayton / Millington Wood Peter Halkon 13/02/08
GB07/03 Mid-Wales Gemma Bell 18/02/08
GB08/11 Broom's Farm Doreen Boyd 01/07/08
CEH07/02 Stanlow Andrew Wilson 04/07/08
GB07/05 Loch Leven/Estwaite/Windermere Andrew Tyler 2007
UR08/01 Black Venn Andrew Ford 2008
UR08/02 River Coquet Andrew Large 2008
GB08/01 Wales Geraint Vaughan 2008
GB08/03 Peak District Richard Armitage 2008
GB08/18 River Frome Richard Stillman 2008
IPY07/09 Iceland Tim Wright 2008
NL08/01 Netherlands Hugh Coe 2008

Unsupported projects in the 2008 flying season (these projects were NOT rolled over to the 2009 flying season)

GB08/16 River Feshie James Brasington
GB08/17 Coed Y Brenin Ross Hill
GB08/05 Dee Estuary Alejandro Souza
GB08/07 Forby+ Alejandro Souza
GB08/09 Idle valley Malcolm Lillie
VA08/01 Chile Geraint Vaughan

Special or specific considerations

Project Location PI Status Comments
GB05/07 Severn, Stour & Thames Paul Bates Contingency project May be concluded/withdrawn
CEH07/05 Wytham Wood Andrew Wilson Repeat Project - partially supported 18/02/08May be concluded/withdrawn, see GB08/08
HY05/04 Thameshaven Andrew Wilson May be concluded/withdrawn
GB05/13 Plymouth Peter Land Partially supported May be concluded/withdrawn
CEH07/01 Buckingham Andrew Wilson Partially supported May be concluded/withdrawn. Data partially recovered!
GB06/07 Silverflowe Andrew Wilson Partially supported May be concluded/withdrawn

Atmospheric projects

Project Location PI Status Data collection Comments
GB08/01 Oxford to Haverfordwest Nigel Langford| | February
GB09/01 Wales Geraint Vaughan March
GB09/02 TBA Martin Gallagher Pilot March To be supported with GB09/01